05
Jan

FIRMS SHORTLISTED FOR NAVI MUMBAI AIRPORT SAY IT WILL TAKE 6 YEARS TO BUILD

Times of India

Link to news article

The Navi Mumbai international airport may miss its 2019 deadline with three of the qualified bidders raising questions about the timeline and cost overurns involved in executing the Rs 16,000-crore project.

Sources from one of the construction firms involved in the bidding said it would take at least six years from “start to finish” to complete the new airport given the current status at the site (see graphic). However, Cidco still claims that one runway will be operational by 2019 and the entire airport ready the following year.

Tata Realty & Infrastructure, Hiranandani Group and GMR Infrastructure have said that they do not plan to put in financial bids on January 9 and will seek time to decide till issues linked to resettlement and pre-development work are resolved.GVK Power & Infrastructure-led Mumbai International Airport (MIAL) is the fourth bidder and the only one that has not expressed reluctance to meet the 42-month deadline which government intends to set.

A Tata Realty official said the deadline set by City and Industrial Development Corporation (Cidco), a planning agency of the state government, was “ridiculous”.”The corporation want us to complete the work within three-and-a-half years when the ground leveling work itself will take over two years,” he said.

Some of the bidders also cited a potential conflict of interest saying ground leveling work has been awarded to the subsidiary of one of the four bidders. “If the ground leveling work is deliberately delayed or not done properly , the winning bidder will face penalties or even face termination of contract.This is unfair,” they said.

Darshan Hiranandani, whose construction firm has qualified along with Zurich Airport to bid for the project, said, “We strongly suggest Cidco think out of the box the way our country is currently doing.” He said the corporation has still not received the final environmental clearance and hence all are “skeptical what riders it will come with”.

“Land development work contracted or awarded has still not begun to convert into action. “Two tenders for land development have been scrapped, thereby creating worries on the timeline,” he added. Bidders are concer ned about the consequent impact on the cost of the project and whether the estimates provided by government are sufficient.

GMR has said more than 3,200 families need to be relocated from the site before work starts. “Agencies appointed for two land development work packages have not been able to start the survey due to protests from local villagers. Any further delay in rehabilitating these families will have a compounding effect on project completion schedules,” it said. Cidco MD Bhushan Gag rani, however, said all the issues which are being raised by bidders have been discussed multiple times with them over the past four years.”These are all old issues and they are aware of them. We have granted them enough extensions to submit their bids,” he told TOI.

Gagrani admitted that the timeline for completion is tight. “Cidco will remove project-affected persons from the site, so they should not worry about it. The pending environmental clearances too have nothing to do with their work,” he added. Gagrani said the entire project would be completed by 2020. “Cidco will invest up to Rs 2,000 crore for site development,” he said.

 Activists have cautioned that the Navi Mumbai site is surrounded by rich bird habitats. “It involves destruction of 400 acres of mangroves, 1,000 acres of mud flats and about 300 acres of forest land. Two rivers will have to be diverted. The Rs.6,500 crore that will be spent on “land development” is actually the cost of destroying the environment,” said environmentalist Debi Goenka.

 TIMES VIEW:

 For bidders to raise questions about delays and cost escalation in the execution of such a prestigious project is a matter of concern. The Navi Mumbai airport is of vital importance to the growth of the region and is the only answer to the bottlenecks which prevent expansion at the existing Mumbai facility.The BJP government in the state could score big brownie points if it displays the will to commission the airport even partly by 2019 during its present term. The administration must provide necessary support to CIDCO to ensure the deadline is met.

You are donating to : CAT

How much would you like to donate?
$10 $20 $30
Would you like to make regular donations? I would like to make donation(s)
How many times would you like this to recur? (including this payment) *
Name *
Last Name *
Email *
Phone
Address
Additional Note
paypalstripe
Loading...